picote brush coating crew green moles limassol 01

Limassol, Cyprus

Picote Solutions Partner Green Moles

Picote Brush Coating™
in 14 Roof Drains

Location:
Limassol, Cyprus
Year:

2020

Work:
  • Drain cleaning
  • Picote Brush Coating™
Time frame:
5 days
Pipe:

14 PVC Roof Drains

Introduction

In 2020 Green Moles won a contract to find a renovation solution for 14 rainwater drains in a multi-storey residential building in Limassol, Cyprus.

The internal inspection of the roof drains showed defects in every pipe, including blockages, many holes from screws and faulty joints.

picote brush coating crew green moles limassol 03

Issues and Challenges

All drains were installed inside reinforced concrete pillars, leaving no option to simply dig and replace.
Every roof drain had branches connected from the balconies of each floor. All balcony drains had built-in traps and grilles under the floor tiles.

To line the pipe would require digging out the traps to open direct access to each drain pipe and reinstate connections to the stack. This could cause significant disruption.

In addition, the building had just undergone a major and expensive renovation involving the installation of thermal insulation to the external walls. It would have been unsightly to install external drains.

picote brush coating pipe blockage green moles limassol 01

Implementation

Thanks to the small size and low weight of the Mini Millers and Picote Brush Coating™ equipment, it was possible to lift them to the top floor using the small elevator of the building. From there they were manually carried to the roof from the stairs.

Two teams with two Picote Brush Coating™ systems were engaged in this project to enable completion as quickly as possible. The weather forecast announced heavy rain in the upcoming days and so the clock was ticking! 

Day 1: One crew unblocked and cleared all 14 drains of debris and other material. They used Picote PVC Chains which are the most suitable for work in fragile pipes.

Day 2: All 14 drains were abraded using  Mini Millers and Picote Smart Cutter™ to prepare the pipes for coating.

Day 3, 4 & 5:  Picote Brush Coating™ begins! Teams applied 2-3 layers of epoxy resin in each drain. CCTV inspections followed each layer to ensure even coverage. The Dual Colour 100% Solids Epoxy made it simple to visually verify any spots that might have been missed. The Smart Mixer 2.0 ensured a simple and mess free application with minimal waste.

picote brush coating broken pipe green moles limassol 01

Benefits

  • Quick delivery and short project duration
  • Lightweight equipment for access
  • Cost-saving trenchless repair avoiding damage to newly installed insulation
  • No disruption for the residents